Workers finish 8th floor of QEII Halifax Infirmary Tower project

The province is celebrating what it calls a “milestone” in the QEII Halifax Infirmary Tower project, releasing new numbers on how many resources are needed to construct the multi-billion-dollar project.

Workers have reached level eight podium, meaning they are over halfway to finishing the 14-storey acute care tower. When complete, it’ll have medical device reprocessing, a larger emergency department, surgical suites, ambulance treatment spaces and laboratories.

According to the Nova Scotia government, the project was named Best Social Infrastructure Project recently, which recognizes excellence in public-private partnerships in the province.

The building installation began this summer, and saw hundreds of workers daily moving around the site, laying rebar and pouring concrete.

According to the release crews have:

  • Surpassed one million hours worked with zero lost-time incidents
  • Excavated and removed 543,000 tonnes of soil and rock
  • Poured 54,000 cubic metres of concrete
  • Installed 5,800 tonnes of steel and rebar
  • Installed 22 concrete girder beams weighing more than 907,000 kilograms combined

“Hundreds of people have worked together to bring this building to life, while maintaining an active hospital campus and keeping patients, visitors and staff moving safely through it,” David Benoit, President and CEO, Build Nova Scotia, said.

The structure’s underground electrical work, permanent power, and systems were started this year, and are continuing. Over the next year, the tower is expected to be completed.

It’s set to be turned over to Nova Scotia Health where staff will be trained, ahead of receiving its first patients in the fall of 2031.

The cost estimate under the agreement with Plenary PCL Health, includes $4.5 billion to construct the tower at the Halifax Infirmary and $2.9 billion over 30 years to operate and maintain the new building.

Workers install reinforcing steel as construction of the new acute care tower progresses at the QEII Halifax Infirmary. To date, 5,800 tonnes of steel and rebar have been installed as part of the project. (Build Nova Scotia)